Transformer Sizing Calculator

Pick the standard transformer kVA for a connected load with sensible headroom, or work out the primary and secondary full-load currents of a transformer you already have.

Last checked against the code

Transformer Sizing Calculator

NEC (US)
What do you need?
How is the load given?
Phase
Does not change the kVA arithmetic — kVA is kVA either way. It is asked because the real size ladders differ by phase, and the result says where they do.
Phase
Here it is in the arithmetic — three-phase divides by 1.732 as well as by the voltage.
Caution: Standard sizes are a market list, not a code table. No NEC article publishes a ladder of transformer kVA ratings the way 240.6(A) publishes breaker ratings. These are what manufacturers commonly build and distributors commonly stock, and they vary by product line, enclosure type and utility. Confirm the rating is actually available before specifying it.

How this is calculated

Note: Sizing is a design decision; protecting it is a code one. Nothing in the NEC tells you how much headroom to carry — that is engineering judgement about growth and money. What the code does govern is the overcurrent protection once the transformer exists, and 450.3 sets that separately for each side from that side's full-load current. This page does the first job and hands off the second.

Start in apparent power. What limits a transformer is heat in the windings, and heat comes from current whether or not that current does useful work — which is why the nameplate is in kVA and why it is independent of what the load's power factor happens to be. A figure quoted in kilowatts has to be converted before anything else: kVA = kW ÷ power factor.

Then add headroom. Multiply the connected load by one plus the margin — 20% is the usual starting point. This is the one number on the page that is pure judgement. Too little and the building outgrows the transformer; too much and the owner pays for iron that spends its life warm and idle, since no-load losses run whether the transformer is serving anything or not.

Then round up, and watch what the rounding costs. The arithmetic produces a number nobody sells. Standard sizes go 15, 25, 37.5, 50, 75, 100, 112.5, 150, 225, 300 — and the gaps widen as you climb. A requirement of 51 kVA buys a 75; one of 310 buys a 500. That rounding routinely adds more spare capacity than the headroom you argued over, which is why this calculator shows the raw requirement next to the size rather than only the answer.

Full-load current is the other half of the job, and it is where the code takes over. FLA = (kVA × 1000) ÷ V for single-phase, divided additionally by 1.732 for three-phase. Run it for the primary voltage and again for the secondary and you get two quite different numbers — a 75 kVA 480→208 V transformer draws 90 A on its primary and delivers 208 A from its secondary. Both are needed: 450.3 protects the two sides separately, and the conductors on each side are sized from their own figure.

Worked example

One full calculation with real numbers, so you can follow along and check the tool by hand.

A three-phase load list adds up to 45 kVA. The building is substantially built out but the owner wants normal growth margin, so20% headroom.

Required capacity. 45 × 1.20 = 54 kVA. That is the honest answer to the question as posed, and it is also a transformer that does not exist.

Rounding up. The ladder runs … 37.5, 50,75, 100 … There is nothing in between. 54 does not fit a 50, so the answer is 75 kVA.

What that actually bought. The jump is 75 − 54 =21 kVA of capacity nobody asked for — 39% more than the calculation called for. That is easiest to see in kVA rather than in percentages. The 20% headroom that was asked for is 9 kVA on top of the 45 kVA load. What the ladder actually delivers is 30 kVA of spare capacity above that same load. The rounding, not the specification, is what set the real margin on this transformer.

That is not a mistake, and there is nothing to fix — it is what the ladder does. But it is worth seeing, because it changes the conversation. If the load list were trimmed to 41 kVA the requirement would be 49.2 kVA, which fits a50 — one rung down, and a materially cheaper transformer, pad and set of secondary conductors. Whether that is worth doing depends on how confident anyone is that 41 kVA is really the ceiling.

The same shape appears all the way up the ladder and gets more expensive as it goes. A 310 kVA requirement buys a 500. Anything just over a rung is worth a second look before it is specified.

Visual comparison

What the rounding costsUpdates with your inputs, in sizing mode. The middle bar is what the calculation asked for; it does not fit the rung below it, so it buys the rung above. Everything the top bar has beyond the middle one is capacity the ladder forced on you rather than capacity you chose.
What the rounding costs
SizeBarCapacity (kVA)Note
50 kVA50Too small — does not fit
Required5445 kVA load + 20%
75 kVA7521 kVA above what was needed

Source: Standard kVA ratings — a market list, not a code table

The standard kVA ladder, 15 to 1000The same shape as the breaker ratings ladder, and worse. Steps are 10 to 25 kVA apart at the bottom and 250 kVA apart at the top, so the penalty for landing just above a rung grows sharply with size — 1 kVA over 300 costs you a 500.
The standard kVA ladder, 15 to 1000 — data
RatingkVAkVA
15 kVA15
25 kVA25
37.5 kVA37.5
50 kVA50
75 kVA75
100 kVA100
112.5 kVA112.5
150 kVA150
225 kVA225
300 kVA300
500 kVA500
750 kVA750
1000 kVA1000

Source: Common manufacturer offerings; confirm against the product line

Reference tables

The first table is the ladder itself, with the step to the next rung spelled out so the gaps are readable as numbers rather than only as a shape. The phase column is the honest part: this is a combined list, and the classic single-phase and three-phase series are not the same. 25 and 37.5 kVA are single-phase rungs; 30 and 45 kVA are three-phase rungs that this combined list does not carry at all.

The second table is full-load current for the four voltage combinations that cover most US work, computed rather than transcribed. Use it to sanity-check a figure without opening the calculator, and note how far apart the primary and secondary columns are for the same transformer — that gap is the reason 450.3 treats the two sides as separate problems.

Standard transformer kVA ratings
RatingStep to nextkVAClassic ladderTypically
15 kVA+10BothSmall lighting or control panel. The smallest size in general distribution use.
25 kVA+12.5Single-phaseA classic single-phase rung. Three-phase lines usually jump 15 → 30 instead.
37.5 kVA+12.5Single-phaseSingle-phase series. The three-phase equivalent at this point is 45 kVA.
50 kVA+25BothCommon for a small commercial panel or a shop sub-feed.
75 kVA+25BothOn both ladders, and the first size above the 50/75 gap this page is built around.
100 kVA+12.5Single-phaseSingle-phase series; three-phase lines carry 112.5 kVA at this point.
112.5 kVA+37.5Three-phaseThe workhorse three-phase dry-type size for a 480 V to 208 V step-down.
150 kVA+75BothLarger tenant fit-out or a small industrial panel.
225 kVA+75BothA substantial three-phase distribution transformer.
300 kVA+200BothApproaching the point where the transformer gets its own room or pad.
500 kVA+250BothPad-mount or unit-substation territory.
750 kVA+250BothEngineered installation; secondary conductors are paralleled sets by here.
1000 kVABothThe top of this ladder. Above it, sizing is a study rather than a lookup.
Source: Common manufacturer offerings, not an NEC table. Phase column records which classic ladder each rung belongs to — confirm availability with the supplier.
Full-load current at common voltages
Rating480 V, 3øA208 V, 3øA240 V, 1øA120 V, 1øA
15 kVA18.0441.6462.5125
25 kVA30.0769.4104.17208.33
37.5 kVA45.11104.09156.25312.5
50 kVA60.14138.79208.33416.67
75 kVA90.21208.19312.5625
100 kVA120.28277.58416.67833.33
112.5 kVA135.32312.28468.75937.5
150 kVA180.43416.376251250
225 kVA270.64624.56937.51875
300 kVA360.85832.7412502500
Source: Computed as (kVA × 1000) ÷ (V × 1.732) for three-phase and (kVA × 1000) ÷ V for single-phase, using the same 1.732 the rest of this site uses.

Notes and exceptions

This page does not pick the overcurrent devices. 450.3 is a table of percentages rather than a single rule: what is permitted depends on the transformer's impedance, on whether protection is provided on the primary only or on both sides, and on whether the installation is supervised. Getting that half right would be worse than not doing it, so the calculator produces the two full-load currents and hands them to the breaker size calculator, where the 450.3 percentage for your arrangement gets applied.

Secondary conductors have their own rules. 240.21(C) governs the conductors between a transformer secondary and its overcurrent device, and it is one of the genuinely awkward corners of the code — the permitted arrangements include 10-foot and 25-foot tap rules with different conditions attached. A correctly sized transformer with incorrectly protected secondary conductors is a common finding.

Not every transformer is sized this way. A buck-boost arrangement is rated for the boosted quantity rather than the connected load and comes out far smaller than this calculation would suggest. K-rated and harmonic-mitigating units serving non-linear load carry a derated effective capacity. And a transformer feeding a large motor may be governed by starting inrush rather than by steady-state kVA, which is a different study entirely.

Inrush is a design consideration even on ordinary loads. A transformer energising draws a large magnetising current for a few cycles, which is why its own primary protection is permitted to be well above its full-load current. That is a feature of 450.3 rather than an oversight, and it is the same reasoning that lets a motor breaker sit far above the motor's running current.

Common mistakes

  1. Sizing to exactly 100% of the current connected load

    A transformer matched to today’s load has nothing left for the circuit somebody adds next year, and replacing one means an outage, a crane and a new pad. Carrying 20–25% costs very little at purchase and is the cheapest capacity you will ever buy.

  2. Sizing primary and secondary protection from one current

    They are different numbers — a 75 kVA 480→208 V unit draws 90 A in and delivers 208 A out. NEC 450.3 sets the two sides’ overcurrent protection separately, each from its own full-load current. Using one figure for both starves one side or leaves the other unprotected.

    NEC 2023 450.3

  3. Entering kW where the calculation wants kVA

    A schedule quoting kilowatts gets typed straight into a kVA field and the unit comes out a rung small. The tell is a transformer running hot at a load the paperwork says it should carry comfortably — the power factor was never in the number.

  4. Specifying from a generic ladder rather than the supplier’s

    A 40 kVA three-phase requirement rounds to 50 on the combined list this page carries, but 45 kVA is a catalogue item in most three-phase dry-type lines. Buying a rung you did not need is the cheap version of this error; the expensive version is specifying a rating nobody stocks and finding out at submittal.

  5. Ignoring what the rounding really costs

    The gap between rungs widens as you go up. A requirement of 51 kVA buys a 75, and one of 310 kVA buys a 500. It is worth checking whether trimming the load or the headroom drops you a rung before accepting a design that sits just above a step.

This tool provides planning estimates. Always verify final values against your local code and a licensed electrician.

Frequently asked questions

What size transformer do I need for a 45 kVA load?

With the usual 20% headroom, 45 kVA needs 54 kVA of capacity and the next standard size is 75 kVA — because nothing is built between 50 and 75. That is a common and slightly frustrating result: the transformer ends up 67% larger than the load rather than the 20% that was intended. Trimming the load or the headroom enough to land at or under 50 kVA saves a whole rung.

How much headroom should a transformer have?

20–25% above the connected load is common practice, and it is practice rather than code — no NEC article specifies a growth margin. Less is defensible for a fully built-out space with a fixed load list; more suits a shell building or a tenant fit-out that will change. Very large margins are not free: a lightly loaded transformer spends its life paying no-load losses that are a bigger share of its running cost.

What is the full-load current of a 75 kVA transformer?

It depends which side you ask about, which is the point of asking. At 480 V three-phase the primary draws 90.2 A; at 208 V three-phase the secondary delivers 208.2 A. Same power, lower voltage, so 2.3 times the current. The formula is (kVA × 1000) ÷ (V × 1.732) for three-phase, or (kVA × 1000) ÷ V for single-phase.

Does a transformer need protection on both sides?

Usually, and NEC 450.3 governs it. The permitted percentages depend on the transformer’s impedance, on whether protection is provided on the primary only or on both sides, and on whether the location is supervised — a primary-only arrangement is permitted in defined circumstances, with a lower percentage than a both-sides arrangement allows. This calculator gives you the two full-load currents; the 450.3 table decides what device each one takes.

Why is a transformer rated in kVA and not kW?

Because what limits a transformer is heat in the windings, and heat comes from current regardless of whether that current is doing useful work. A load with a poor power factor draws more current for the same kilowatts, and the transformer feels all of it. Rating in apparent power makes the nameplate independent of the load’s power factor, which is why the calculation converts kW to kVA rather than the other way round.

Can I load a transformer to 100% of its nameplate?

Continuously, it is generally not what you want. The nameplate rating assumes a defined ambient temperature and cooling arrangement, and running at it leaves nothing for a hot day, a blocked ventilation path or the load growing. Some units carry a fan-cooled rating above the self-cooled one, which is a specific tested figure rather than a general allowance — check the nameplate rather than assuming headroom exists.