Cable Size Calculator
Size a cable in mm² for a load and a run length the way BS 7671 and AS/NZS 3008 do it — current rating by installation method, voltage drop by mV/A/m — with the tool naming which of the two decided the answer.
Last checked against the code
Cable Size Calculator
BS 7671 (UK)Other standards: NEC (US), in AWG
Recommended cable
—
The two checks, run separately
Minimum by current rating
—
Minimum by voltage drop
—
- Voltage drop at this sizemV/A/m × amps × metres
- ——
- Current rating at this size
- —
Ambient temperature, grouping and thermal-insulation factors are not applied here — each of them derates the current rating further, and a circuit that is close on the rating check should be re-run with them.
How this is calculated
A cable has to pass two tests, and this calculator runs both and gives you whichever demands the larger conductor. It has to carry the current without cooking its own insulation, and it has to reach the accessory with enough volts left to run whatever is plugged into it. Those are unrelated failure modes and either can be the one that governs.
Test one is the current rating. Here is the first real difference from American practice. The NEC publishes one ampacity per conductor and then multiplies it by correction factors for the conditions. BS 7671 publishes a separate rating column for each installation method — so how the cable is installed decides which number you start from, not what you multiply. A 2.5 mm² copper cable is rated 27 A clipped direct, 24 A in conduit and 30 A in free air: three different starting points for one cable. Choosing the method is therefore part of the sizing, not an adjustment applied afterwards, and the four presets here stand in for BS 7671's reference methods B, C, D and E/F.
Test two is voltage drop, and it uses mV/A/m. This is the bigger conceptual difference. The NEC-based pages on this site reconstruct the cable's resistance from first principles every time: a resistivity constant, the length, and the conductor area in circular mils. The metric standards skip all of that by publishing the finished answer for each size — the millivolts that cable drops per amp carried per metre run. The calculation collapses to one multiplication:
Vdrop (mV) = (mV/A/m) × Ib × L, divided by 1,000 for volts, then taken as a percentage of the supply voltage.
There is no conductor area in that formula and no resistivity constant, because the table already accounted for both. There is also no √3. Three-phase drop is its own published column rather than a multiplier applied to the single-phase figure, which is why nothing in this calculator's code multiplies by 1.732 — the phase relationship was handled by whoever compiled the table. The trade is transparency for reliability: you cannot see the physics working, but there is correspondingly less to get wrong.
The drop target is different too. BS 7671 gives 3% for lighting and 5% for other uses, measured from the origin of the installation. The 4% this page defaults to is not in the regulations — it is the general working figure a lot of UK design practice lands on, and it is the default because the calculator does not ask what the circuit feeds. The NEC's commonly cited 3% is a different number from a different document measuring from a different point, so it is not a figure to carry across.
Worked example
One full calculation with real numbers, so you can follow along and check the tool by hand.
A 25 A design current on a 230 V single-phase supply, copper cable clipped direct,20 metres from the board, against a 4% drop target.
The current-rating path. Reading down the clipped-direct column: 1.5 mm² is rated 20 A, short of 25. 2.5 mm² is rated27 A, which clears it with2 A to spare. The rating-constrained answer is2.5 mm².
The voltage-drop path. The budget is 4% of 230 V =9.2 V, or 9200 mV. Spread over 25 A × 20 m = 500 amp-metres, that allows a cable of no worse than18.4 mV/A/m. 2.5 mm² is18 mV/A/m, which just fits. The drop-constrained answer is 2.5 mm² as well.
The answer. Both checks land on2.5 mm², so neither one "wins" — this is the balanced point for the circuit. The actual drop is18 × 25 × 20 =9,000 mV =9 V, which is 3.91%of 230 V. The load sees 221 V.
And now the part worth remembering. That result clears the 4% target by 0.09 of a percentage point. At 25 A this cable runs out at about 20.4 m — so a route that turns out to be 21 metres rather than20 needs 4 mm², one full size up, and the binding constraint flips to voltage drop. A single metre of unmeasured route between the board and the accessory is the entire margin. This is exactly why measuring along the cable rather than across the drawing matters more on metric domestic work than the numbers suggest: at 230 V the volt budget is half what a 400 V or 480 V circuit gets, and circuits sit much closer to their limits.
Visual comparison
- Minimum by voltage drop
- Minimum by current rating
| One-way run (m) | Minimum by voltage dropmm² | Minimum by current ratingmm² | Which binds, and at what size |
|---|---|---|---|
| 10 | 1.5 | 2.5 | 2.5 mm² — rating wins over 1.5 mm² |
| 20 | 2.5 | 2.5 | 2.5 mm² either way |
| 30 | 4 | 2.5 | 4 mm² — drop wins over 2.5 mm² |
| 40 | 6 | 2.5 | 6 mm² — drop wins over 2.5 mm² |
| 50 | 6 | 2.5 | 6 mm² — drop wins over 2.5 mm² |
| 60 | 10 | 2.5 | 10 mm² — drop wins over 2.5 mm² |
| 70 | 10 | 2.5 | 10 mm² — drop wins over 2.5 mm² |
| 80 | 10 | 2.5 | 10 mm² — drop wins over 2.5 mm² |
| 90 | 16 | 2.5 | 16 mm² — drop wins over 2.5 mm² |
| 100 | 16 | 2.5 | 16 mm² — drop wins over 2.5 mm² |
Source: Illustrative ratings and mV/A/m figures — see the note under the reference table
At 25 A clipped direct on a 230 V supply, voltage drop overtakes the current rating at about 30 m. Below that length the design current chooses the cable; above it the route does.
Reference tables
This is the table the calculator reads. It is worth having open rather than running a calculation when you are checking a design someone else produced, or when you want to see how much a different installation method would buy you before committing to a route.
Read the four rating columns as four different cables. They are the same conductor in four thermal environments, and the spread between the worst and the best is around 40% at every size — a bigger effect than one step up the size ladder. The mV/A/m columns, by contrast, do not move with installation method at all: voltage drop is a property of the conductor, not of what surrounds it. That asymmetry is the single most useful thing on this page. If a design fails on the rating check, changing how it is installed may fix it; if it fails on drop, only a bigger cable, a shorter route or a higher voltage will.
Aluminium is offered from 16 mm² up and is not listed below that, so the copper table is shown here. Its ratings run about 22% lower and its mV/A/m about 64% higher than the copper figures at the same size — switch the material in the calculator to see it applied.
These numbers are provisional. They are illustrative placeholders that behave correctly relative to one another, not transcriptions from a published standard — BS 7671 Appendix 4 and AS/NZS 3008 are both commercially licensed, and the two do not agree with each other on reference conditions or installation-method definitions. Cross-check anything you intend to install against the current published table for your own jurisdiction.
| Size | In conduitA | Clipped directA | BuriedA | Free airA | Drop, 1-phmV/A/m | Drop, 3-phmV/A/m |
|---|---|---|---|---|---|---|
| 1 mm² | 13.5 | 15.5 | 14 | 17 | 44 | 38 |
| 1.5 mm² | 17.5 | 20 | 18 | 22 | 29 | 25 |
| 2.5 mm² | 24 | 27 | 24 | 30 | 18 | 15 |
| 4 mm² | 32 | 37 | 31 | 40 | 11 | 9.5 |
| 6 mm² | 41 | 47 | 38 | 51 | 7.3 | 6.4 |
| 10 mm² | 57 | 65 | 50 | 70 | 4.4 | 3.8 |
| 16 mm² | 76 | 87 | 64 | 94 | 2.8 | 2.4 |
| 25 mm² | 101 | 114 | 82 | 123 | 1.75 | 1.5 |
| 35 mm² | 125 | 141 | 98 | 151 | 1.25 | 1.1 |
| 50 mm² | 151 | 182 | 116 | 192 | 0.93 | 0.8 |
| 70 mm² | 192 | 234 | 143 | 246 | 0.63 | 0.55 |
| 95 mm² | 232 | 284 | 169 | 298 | 0.46 | 0.4 |
| 120 mm² | 269 | 330 | 192 | 346 | 0.36 | 0.31 |
| 150 mm² | 309 | 381 | 217 | 399 | 0.29 | 0.25 |
| 185 mm² | 353 | 436 | 243 | 456 | 0.23 | 0.2 |
| 240 mm² | 415 | 515 | 280 | 538 | 0.19 | 0.16 |
| Preset | Reference method | When it applies |
|---|---|---|
| In conduit or trunking | Reference Method B | Enclosed in conduit or trunking on or in a wall. The most restrictive of the four — heat has nowhere to go. |
| Clipped direct | Reference Method C | Clipped to a surface, open to air on one side. The usual case for twin-and-earth on joists or a wall. |
| Buried underground | Reference Method D | Direct in the ground or in a buried duct. Depends heavily on soil thermal resistivity, which this preset assumes rather than measures. |
| Free air / on a tray | Reference Method E or F | Spaced from a surface, on a perforated tray or a ladder. The most generous — air circulates all the way round. |
Notes and exceptions
Which calculator should you be using? If you are working to the NEC — the United States and much of its regulatory orbit — thewire size calculator is the right tool, and it will give you an AWG answer from Table 310.16 with the 125% continuous-load rule applied. If you are working to BS 7671 in the UK or Ireland, or AS/NZS 3008 in Australia and New Zealand, this page follows the method you are used to. The two are not converts of each other and their answers are not interchangeable: the standards differ on reference conditions, on how installation conditions are handled, and on what the voltage-drop limit even is.
What this calculator leaves to you. The correction factors are the biggest omission: ambient temperature (Ca), grouping (Cg), thermal insulation (Ci) and semi-enclosed fuses (Cc) all reduce the current rating, and on a crowded trunking or a hot plant room they reduce it substantially. So does harmonic content on a three-phase circuit with a heavily loaded neutral. Earth fault loop impedance and disconnection times — which frequently drive the CPC size and sometimes the line conductor too — are a separate calculation this page does not attempt. And the drop figure assumes the cable is at its rated operating temperature, which a lightly loaded circuit will not be.
On the tables themselves. This is worth saying twice because it is unusual for this site: every other calculator here transcribes NEC tables that are republished so widely they can be checked against a dozen independent sources. These figures cannot be, because the standards they would come from are licensed documents. They are in the right region and they behave correctly relative to one another, which is enough to demonstrate the method and to size a circuit approximately — but a figure you are going to install needs checking against the real table, and if BS 7671 and AS/NZS 3008 diverge enough to change the recommendation, the honest fix is two tables behind a jurisdiction switch rather than one averaged compromise.
Common mistakes
Sizing from the protective device rating instead of the design current
BS 7671 runs on three separate figures: the design current Ib, the device rating In, and the cable capacity Iz, with Ib ≤ In ≤ Iz. Feeding In into the sizing skips the diversity you already applied and quietly oversizes every circuit on the board.
BS 7671 Regulation 433.1.1
Picking an installation method that flatters the answer
The four presets here differ by roughly 40% at the same size. A cable clipped along a joist and then buried in loft insulation for two metres is not Method C for its whole length — the worst stretch governs, and a short bad section sets the rating.
Ignoring grouping and ambient once a method is chosen
The method column is only the starting figure. Six circuits sharing a trunking, or a run through a 40 °C plant room, apply correction factors on top that this calculator does not model. A result close on the rating check needs those applied before it is safe.
BS 7671 Appendix 4, Tables 4B1 and 4C1
Applying the NEC 3% figure to a UK installation
BS 7671 works to 3% for lighting and 5% for other uses, measured from the origin. Neither number is the American 3% branch-circuit figure, and the two standards define the measuring point differently, so importing a habit from a US calculator gets both the limit and the reference wrong.
BS 7671 Appendix 12
Measuring the route on a drawing rather than along the cable
Run length means the cable, not the plan distance: drops down walls, the climb over a beam, the loop into every accessory and the tail in the board. On a circuit that scrapes the drop limit, 20% of unmeasured route is the whole margin.
This tool provides planning estimates. Always verify final values against your local code and a licensed electrician.
Frequently asked questions
What is the difference between this and the Wire Size Calculator?
They answer the same engineering question in two different regulatory languages. This page works in mm², picks a current rating from the installation method you choose, and calculates voltage drop from a published mV/A/m figure — the BS 7671 and AS/NZS 3008 approach. The Wire Size Calculator works in AWG and kcmil, takes one base ampacity from NEC Table 310.16 and applies correction factors to it, and calculates drop from a resistivity constant and the conductor area. Use this one for UK, Irish, Australian and New Zealand work; use that one for anything under the NEC.
What size cable do I need for a 25 amp load over 20 metres?
On a 230 V single-phase supply in copper, clipped direct, with a 4% drop target: 2.5 mm². Both checks land on it — 2.5 mm² is rated 27 A clipped direct, and at 18 mV/A/m it drops 9.0 V over that run, which is 3.91% of 230 V. It is a genuinely tight fit, and a 21 metre run needs 4 mm².
What is mV/A/m and how do I use it by hand?
It is the millivolts a cable loses per amp it carries per metre it runs, listed against every size in the standard’s tables. Using it is one multiplication and one division: look the number up, multiply by your amps and your metres to get millivolts, divide by 1,000 for volts. A 2.5 mm² cable at 18, carrying 25 A over 20 m, gives 18 × 25 × 20 = 9,000 mV, so 9 V. Compare that against your percentage limit in volts and you are finished — no area, no resistivity, no square roots.
Is the voltage drop limit 3%, 4% or 5%?
BS 7671 gives 3% for lighting circuits and 5% for other uses, measured from the origin of the installation, where the supply comes from a public distribution network. 4% is not in the regulations at all — it is a general working figure that a lot of UK design practice settles on when a circuit is neither pure lighting nor obviously a heavy power load. This calculator defaults to 4% because it does not ask what the circuit feeds; set it to whichever figure actually applies.
Why does aluminium start at 16 mm²?
Below that it is not manufactured or installed as a general wiring cable. Aluminium carries about 61% of the current copper does for the same cross-section and needs a correspondingly larger conductor, so in the small sizes the cable ends up bulkier and more awkward to terminate than the copper it would replace. Its advantages — cost and weight — only appear in the larger sizes, which is where the tables start listing it.
Does this calculator comply with BS 7671 or AS/NZS 3008?
No, and it does not claim to. It follows the general method both standards use, but the tables behind it are illustrative placeholders rather than transcriptions, because both documents are commercially licensed and cannot be republished. The two standards also differ from each other in their reference conditions and installation-method definitions, so no single table is correct for both. Treat this as a planning aid and confirm any figure you are going to install against the current published table for your jurisdiction.