Amps to kVA Calculator
Work backwards from a current you have measured or calculated to the apparent power a transformer, generator or UPS has to be rated for — and the standard size that figure rounds up to.
Last checked against the code
Amps to kVA Calculator
Updates as you type- Next standard ratingThe smallest rung at or above the calculated figure
- —
- Spare capacity at that ratingNot the same as design headroom for growth
- —
kVA = (I × V) ÷ 1,000 single phase · kVA = (I × V × 1.732) ÷ 1,000 three phase
How this is calculated
This is the conversion you reach for when the current is the thing you already know — clamped off an existing feeder, taken from a load schedule, or arrived at as the capacity a new installation has to have — and the equipment you are about to choose is sold by a different measure. Transformers, standby sets and UPS units are specified in kilovolt-amperes, so the current has to be translated before a catalogue is any use.
Volt-amperes are simply volts multiplied by amps. Divide by a thousand for the kilo, and add the three-phase factor where it applies:
Single phase: kVA = (I × V) ÷ 1,000
Three phase: kVA = (I × V × 1.732) ÷ 1,000
The 1.732 is where this conversion goes wrong most often, and it goes wrong quietly. Leave it out and the answer is 42% below where it should be — small enough to look like a reasonable number and large enough to buy a machine that cannot do the job. There is no partial credit here: either the supply has three line conductors and the factor applies, or it has one and it does not.
What the arithmetic produces is a minimum, and treating it as an answer is the second trap. Standard ratings exist in a fixed ladder — 15, 25, 37.5, 50, 75, 112.5, 150, 225 and upward — and nothing is manufactured between the rungs. A figure of 166.27 kVA is not something you can order; it is a threshold that tells you the 150 kVA unit is out and the 225 kVA unit is in.
Two things this conversion deliberately does not do. It applies no power factor, because volts times amps is apparent power by definition and the result is already in the units the nameplate uses. And it adds no design margin: the figure describes the load as entered, with nothing set aside for the circuit somebody adds in four years' time.
Worked example
One full calculation with real numbers, so you can follow along and check the tool by hand.
A 200 A three-phase feeder at 480 V, on a small industrial unit that is getting its own transformer rather than continuing to be fed from the main switchboard.
The conversion. 200 × 480 = 96,000, and because this is a three-phase supply that figure is multiplied by 1.732 to give 166,272 VA, or166.27 kVA. Worth pausing on the intermediate number: 96 kVA is what the naive sum produces, and it is the answer a great many people write down. It is not conservative or approximate — it is 42% short.
Finding the rung. Looking up the standard ladder from 166.27, the next rating is 225 kVA. The one below it is 150 kVA, which is 10% under what the feeder can pass and therefore not a candidate. So the answer is a 225 kVA transformer carrying 58.73 kVA of spare capacity, or 35% above the calculated figure.
Is that spare capacity a bonus? Not quite, and this is where a converter stops being enough. Thirty-five percent sounds like generous room for growth, but it is an accident of where the rungs happen to fall rather than a decision anybody made. Had the feeder been 250 A, the calculation would give 207.84 kVA — still landing on the same 225 kVA unit, but with only 8% to spare and no room at all for the next machine on the floor. Two similar-looking jobs, the same transformer, and completely different amounts of future.
That is the question the sizing calculator answers and this one does not: it applies a headroom percentage before rounding, so growth is something you specify rather than something the ladder hands you at random. Use this page to find out where you stand; use that one to decide what to buy.
Visual comparison
| Current | Apparent powerkVA | Nearest standard rating |
|---|---|---|
| 100 A | 83.14 | Rounds to 100 kVA · 20% spare |
| 200 A | 166.27 | Rounds to 225 kVA · 35% spare |
| 300 A | 249.41 | Rounds to 300 kVA · 20% spare |
| 400 A | 332.54 | Rounds to 500 kVA · 50% spare |
| 600 A | 498.82 | Rounds to 500 kVA · 0% spare |
| 800 A | 665.09 | Rounds to 750 kVA · 13% spare |
| 1,000 A | 831.36 | Rounds to 1000 kVA · 20% spare |
| 1,200 A | 997.63 | Rounds to 1000 kVA · 0% spare |
Source: Currents are standard overcurrent ratings; kVA calculated at 480 V three-phase.
Reference tables
This table starts from the ratings services and feeders are actually built at, which is the number most readers arrive with — a 400 A switchboard, an 800 A main, a breaker frame size off a drawing. Look up the row, read across to the supply you are working on, and the last column names the transformer rung that figure rounds up to at 480 V.
Use it instead of the converter when you are scoping rather than calculating: checking roughly what a service would need if it were transformed, or sanity-testing a proposal someone has already put in front of you. The converter is the better tool the moment your current is a real measured or calculated figure rather than a standard rating, because those almost never fall on one of these rows.
The two three-phase columns are worth comparing directly. The same current at 480 V represents 2.3 times the apparent power it does at 208 V, which is the entire argument for distributing at the higher voltage: more power down the same size of conductor. The 240 V single-phase column is there for context and is the one to use for a residential service or a small shop.
The rounding column is a starting point and not a specification. It applies no headroom, and it reads from a combined ladder that includes rungs which only exist on one phase's series in the real market.
| RatingA | 240 VkVA, 1-phase | 208 VkVA, 3-phase | 480 VkVA, 3-phase | Rounds to at 480 V |
|---|---|---|---|---|
| 100 | 24 | 36 | 83.1 | 100 kVA |
| 110 | 26.4 | 39.6 | 91.4 | 100 kVA |
| 125 | 30 | 45 | 103.9 | 112.5 kVA |
| 150 | 36 | 54 | 124.7 | 150 kVA |
| 175 | 42 | 63 | 145.5 | 150 kVA |
| 200 | 48 | 72.1 | 166.3 | 225 kVA |
| 225 | 54 | 81.1 | 187.1 | 225 kVA |
| 250 | 60 | 90.1 | 207.8 | 225 kVA |
| 300 | 72 | 108.1 | 249.4 | 300 kVA |
| 350 | 84 | 126.1 | 291 | 300 kVA |
| 400 | 96 | 144.1 | 332.5 | 500 kVA |
| 450 | 108 | 162.1 | 374.1 | 500 kVA |
| 500 | 120 | 180.1 | 415.7 | 500 kVA |
| 600 | 144 | 216.2 | 498.8 | 500 kVA |
| 700 | 168 | 252.2 | 582 | 750 kVA |
| 800 | 192 | 288.2 | 665.1 | 750 kVA |
| 1000 | 240 | 360.3 | 831.4 | 1000 kVA |
| 1200 | 288 | 432.3 | 997.6 | 1000 kVA |
Common mistakes
Leaving the 1.732 out on a three-phase supply
The error this page exists to catch. Multiplying only amps by volts on a three-phase system understates the answer by 42%: 200 A at 480 V comes out as 96 kVA instead of 166.27 kVA. Nothing about 96 looks wrong, so it gets ordered — and the machine that arrives runs hot from day one.
Feeding in a measured peak instead of a calculated demand
A clamp meter reading caught during a compressor start is not the load. Take a demand figure over a representative period, or a calculated load under Article 220, and treat instantaneous peaks as a separate question about starting capacity.
Ordering the raw number with no room to grow
The converted figure is what today’s load needs at this instant. Equipment lasts decades and loads only ever go up. The transformer sizing calculator adds a design headroom percentage on top before it rounds, which is a deliberate step rather than an afterthought.
Applying power factor on the way out
Current times voltage is apparent power by definition, so the answer is already in kVA. Multiplying by 0.8 to "get the real load" produces kW, which is a different quantity and the wrong basis for sizing a transformer or a set.
Mixing a service rating with an actual load
A 400 A service is what the equipment is rated to pass, not what the building draws. Converting the rating gives the capacity of the supply; converting the calculated load gives what the transformer feeding it has to carry. They are rarely the same number.
This tool provides planning estimates. Always verify final values against your local code and a licensed electrician.
Frequently asked questions
How many kVA is 200 amps?
It depends entirely on the voltage and the phase. At 240 V single phase it is 48 kVA. At 208 V three phase it is 72.05 kVA. At 480 V three phase it is 166.27 kVA — nearly three and a half times the single-phase answer from the same current. Anyone quoting a kVA figure from a current alone has left out the two pieces of information that actually determine it.
Why multiply by 1.732 on three phase?
Because the line-to-line voltage and the current in any one conductor are not in step with each other across the three phases. The square root of three is the factor that reconciles them, and it comes out of the geometry of three waveforms 120 degrees apart rather than from any regulation. The practical consequence is that a three-phase supply moves 73% more apparent power than a single-phase supply at the same voltage and the same current per conductor.
Do I round the answer up or down to pick equipment?
Always up, and usually by more than the next rung. The calculated figure is a minimum: a transformer or generator rated below it will be running past its nameplate whenever the load is at its peak. Standard ratings are spaced unevenly, so how much spare capacity rounding buys varies enormously — 400 A at 480 V lands on a 500 kVA unit with 50% to spare, while 600 A at the same voltage lands on the same 500 kVA unit with almost none.
Is this the same as converting amps to kW?
No. This gives apparent power, which is what equipment nameplates are written in and what sizing decisions are made on. Real power in kW is smaller by the power factor: a 166.27 kVA load at 0.85 is 141 kW. Use kVA for choosing the transformer, generator or UPS, and kW when you are talking about energy, fuel consumption or an engine’s mechanical output.
Can I size a generator directly from this figure?
It is the right starting point for the running load, but not the whole specification. A set also has to swallow the inrush when the largest motor on it starts, which can be several times that motor’s running current and briefly dwarfs everything else on the list. A generator chosen purely on steady-state kVA will stall or trip on that first start.
My reading is per phase — do I still use the same formula?
Yes, provided the load is reasonably balanced and you use the current in one line conductor, not the sum of all three. The formula already accounts for there being three of them. Where the phases are visibly unbalanced, take the highest of the three readings: that conductor and its winding are the ones that will reach their limit first.